Project Start Date: Fri 12/14/01
Project Finish Date: Fri 5/31/02
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
|---|---|---|---|---|---|---|
| 1 | Microsoft Windows NT Server to Windows 2000 Deployment Template | 120.5 days | Fri 12/14/01 | Fri 5/31/02 | 30% | |
| 2 | Vision/Scope | 21.75 days | Fri 12/21/01 | Tue 1/22/02 | 99% | |
| 3 | Evaluate Active Directory features | 1 wk | Fri 12/21/01 | Fri 12/28/01 | 100% | |
| 4 | Evaluate university's objectives | 1 wk | Fri 12/21/01 | Fri 12/28/01 | 100% | |
| 5 | Determine technology goals and objectives | 1 wk | Fri 12/28/01 | Fri 1/4/02 | 100% | |
| 6 | Formulate preliminary cost/benefit analysis | 1 wk | Thu 1/3/02 | Thu 1/10/02 | 100% | |
| 7 | Determine project scope (lab, pilot, international/regional deployment, coexistence strategies, etc) | 1 wk | Thu 1/10/02 | Thu 1/17/02 | 100% | |
| 8 | Determine major milestones | 2 days | Thu 1/17/02 | Mon 1/21/02 | 100% | |
| 9 | Secure executive sponsorship/funding | 1 day | Mon 1/21/02 | Tue 1/22/02 | 100% | |
| 10 | Vision/scope complete | 0 days | Tue 1/22/02 | Tue 1/22/02 | 0% | |
| 11 | Planning | 48.75 days | Fri 12/14/01 | Thu 2/21/02 | 54% | |
| 12 | Assemble Project Teams/Define Roles | 27.5 days | Fri 12/14/01 | Tue 1/22/02 | 75% | |
| 13 | Core Roles | 0.5 days | Tue 1/22/02 | Tue 1/22/02 | 75% | |
| 14 | Project manager | 4 hrs | Tue 1/22/02 | Tue 1/22/02 | 100% | |
| 15 | Infrastructure administrator | 4 hrs | Tue 1/22/02 | Tue 1/22/02 | 100% | |
| 16 | Departmental liason | 4 hrs | Tue 1/22/02 | Tue 1/22/02 | 0% | |
| 17 | Departmental administrators | 4 hrs | Tue 1/22/02 | Tue 1/22/02 | 100% | |
| 18 | Amaint administrator | 4 hrs | Tue 1/22/02 | Tue 1/22/02 | 100% | |
| 19 | Network administrator | 4 hrs | Tue 1/22/02 | Tue 1/22/02 | 100% | |
| 20 | Communication facilitator | 4 hrs | Tue 1/22/02 | Tue 1/22/02 | 100% | |
| 21 | Logistics management | 4 hrs | Tue 1/22/02 | Tue 1/22/02 | 0% | |
| 22 | Core roles complete | 0 days | Tue 1/22/02 | Tue 1/22/02 | 0% | |
| 23 | Assemble project teams/roles complete | 0 days | Fri 12/14/01 | Fri 12/14/01 | 0% | |
| 24 | Detail Current Computing Environment | 15.25 days | Fri 12/14/01 | Fri 1/4/02 | 63% | |
| 25 | Detail technical requirements - vision scope | 1 wk | Fri 12/21/01 | Fri 12/28/01 | 100% | |
| 26 | Detail geographic considerations | 1 wk | Fri 12/21/01 | Fri 12/28/01 | 100% | |
| 27 | Detail information architecture/flow | 1 wk | Fri 12/21/01 | Fri 12/28/01 | 100% | |
| 28 | Detail application requirements | 1 wk | Fri 12/14/01 | Fri 12/21/01 | 0% | |
| 29 | Detail technology architecture | 1 wk | Fri 12/21/01 | Fri 12/28/01 | 100% | |
| 30 | Detail server hardware and software inventory | 1 wk | Fri 12/21/01 | Fri 12/28/01 | 100% | |
| 31 | Detail current and future information technology standards | 1 wk | Fri 12/14/01 | Fri 12/21/01 | 0% | |
| 32 | Document current computing environment | 1 wk | Fri 12/28/01 | Fri 1/4/02 | 0% | |
| 33 | Detail current computing environment complete | 0 days | Fri 1/4/02 | Fri 1/4/02 | 0% | |
| 34 | Identify Coexistence Strategies | 3 days | Fri 12/14/01 | Wed 12/19/01 | 0% | |
| 35 | Identify interoperability issues within the company (operating systems supported, topology, protocol, etc.) | 3 days | Fri 12/14/01 | Wed 12/19/01 | 0% | |
| 36 | Identify coexistence strategies complete | 0 days | Wed 12/19/01 | Wed 12/19/01 | 0% | |
| 37 | Establish Test Lab Environment | 31.5 days | Fri 12/21/01 | Tue 2/5/02 | 93% | |
| 38 | Review current configuration documents and define a lab model | 2 days | Fri 12/21/01 | Tue 12/25/01 | 100% | |
| 39 | Select one or more lab locations | 1 day | Tue 12/25/01 | Wed 12/26/01 | 100% | |
| 40 | Determine lab space and environmental requirements | 1 day | Wed 12/26/01 | Thu 12/27/01 | 100% | |
| 41 | Determine power and network connection requirements | 2 days | Thu 12/27/01 | Mon 12/31/01 | 100% | |
| 42 | Design and document logical and physical configuration for the lab | 2 days | Mon 12/31/01 | Wed 1/2/02 | 50% | |
| 43 | Determine hardware requirements | 2 days | Wed 1/2/02 | Fri 1/4/02 | 100% | |
| 44 | Determine software requirements, including business applications and tools | 3 days | Fri 1/4/02 | Wed 1/9/02 | 100% | |
| 45 | Determine who needs to use the lab | 1 day | Wed 1/9/02 | Thu 1/10/02 | 100% | |
| 46 | Determine Amaint requirements | 1 day | Thu 1/10/02 | Fri 1/11/02 | 75% | |
| 47 | Determine wiring and network tap plans | 1 day | Fri 1/11/02 | Mon 1/14/02 | 100% | |
| 48 | Acquire hardware, including cables and software | 3 days | Mon 1/14/02 | Thu 1/17/02 | 100% | |
| 49 | Acquire workspace equipment, such as desks, chairs, white boards, cork boards, lamps, telephones, and shelving | 3 days | Mon 1/14/02 | Thu 1/17/02 | 100% | |
| 50 | Build and configure the network | 3 days | Thu 1/17/02 | Tue 1/22/02 | 100% | |
| 51 | Test network connectivity | 1 day | Tue 1/22/02 | Wed 1/23/02 | 100% | |
| 52 | Build and configure the servers | 2 days | Wed 1/23/02 | Fri 1/25/02 | 100% | |
| 53 | Install applications and build databases on the servers | 2 days | Fri 1/25/02 | Tue 1/29/02 | 100% | |
| 54 | Install testing and administrative tools | 4 hrs | Fri 1/25/02 | Mon 1/28/02 | 100% | |
| 55 | Build and configure the client computers | 2 days | Fri 1/25/02 | Tue 1/29/02 | 100% | |
| 56 | Test all the lab components | 2 days | Tue 1/29/02 | Thu 1/31/02 | 100% | |
| 57 | Define a change control process for the lab | 4 hrs | Thu 1/31/02 | Fri 2/1/02 | 0% | |
| 58 | Create, test, and document the lab restore process | 2 days | Fri 2/1/02 | Tue 2/5/02 | 50% | |
| 59 | Establish test lab environment complete | 0 days | Mon 1/21/02 | Mon 1/21/02 | 0% | |
| 60 | Perform Risk Assessment | 12 days | Tue 2/5/02 | Thu 2/21/02 | 17% | |
| 61 | Identify mission critical applications | 2 days | Tue 2/5/02 | Thu 2/7/02 | 0% | |
| 62 | Identify and analyze potential risks | 4 days | Thu 2/7/02 | Wed 2/13/02 | 50% | |
| 63 | Quantify potential impact of the risk | 2 days | Wed 2/13/02 | Fri 2/15/02 | 0% | |
| 64 | Detail escalation processes | 2 days | Fri 2/15/02 | Tue 2/19/02 | 0% | |
| 65 | Document risk assessment | 2 days | Tue 2/19/02 | Thu 2/21/02 | 0% | |
| 66 | Risk assessment complete | 0 days | Thu 2/21/02 | Thu 2/21/02 | 0% | |
| 67 | Define Communication Strategy | 13 days | Fri 12/14/01 | Wed 1/2/02 | 0% | |
| 68 | Define communication strategy for each phase | 3 days | Fri 12/14/01 | Wed 12/19/01 | 0% | |
| 69 | Define audiences | 1 day | Wed 12/19/01 | Thu 12/20/01 | 0% | |
| 70 | Define communication delivery mechanism | 3 days | Thu 12/20/01 | Tue 12/25/01 | 0% | |
| 71 | Establish communication timeline | 4 days | Tue 12/25/01 | Mon 12/31/01 | 0% | |
| 72 | Document communications strategy/standards | 2 days | Mon 12/31/01 | Wed 1/2/02 | 0% | |
| 73 | Communication complete | 0 days | Wed 1/2/02 | Wed 1/2/02 | 0% | |
| 74 | Define Education/Training Strategy | 9 days | Fri 12/14/01 | Thu 12/27/01 | 0% | |
| 75 | Define education strategy for deployment demographics (admins, help desk, end-users) | 2 days | Fri 12/14/01 | Tue 12/18/01 | 0% | |
| 76 | Define education delivery mechanism | 2 days | Tue 12/18/01 | Thu 12/20/01 | 0% | |
| 77 | Establish education timeline by phase | 3 days | Thu 12/20/01 | Tue 12/25/01 | 0% | |
| 78 | Document education strategy/standards | 2 days | Tue 12/25/01 | Thu 12/27/01 | 0% | |
| 79 | Education complete | 0 days | Thu 12/27/01 | Thu 12/27/01 | 0% | |
| 80 | Planning complete | 0 days | Thu 2/21/02 | Thu 2/21/02 | 0% | |
| 81 | Development | 97.5 days | Fri 12/14/01 | Tue 4/30/02 | 33% | |
| 82 | Evaluate Migration Strategies | 7 days | Thu 2/21/02 | Mon 3/4/02 | 43% | |
| 83 | Determine your migration roadmap | 1 day | Thu 2/21/02 | Fri 2/22/02 | 0% | |
| 84 | Determine supported upgrade paths | 2 days | Fri 2/22/02 | Tue 2/26/02 | 50% | |
| 85 | Examine your existing domain structure | 2 days | Tue 2/26/02 | Thu 2/28/02 | 100% | |
| 86 | Develop your recovery plan | 2 days | Thu 2/28/02 | Mon 3/4/02 | 0% | |
| 87 | Evaluate migration strategies complete | 0 days | Mon 3/4/02 | Mon 3/4/02 | 0% | |
| 88 | Active Directory | 97.5 days | Fri 12/14/01 | Tue 4/30/02 | 80% | |
| 89 | Active Directory and Domain Namespace | 41.75 days | Mon 3/4/02 | Tue 4/30/02 | 80% | |
| 90 | Review Active Directory features | 3 days | Mon 3/4/02 | Thu 3/7/02 | 100% | |
| 91 | Design Active Directory Forest Plan | 38.75 days | Thu 3/7/02 | Tue 4/30/02 | 79% | |
| 92 | Determine the number of forests for the network | 2 days | Thu 3/7/02 | Mon 3/11/02 | 100% | |
| 93 | Define a forest change control policy | 2 days | Mon 3/11/02 | Wed 3/13/02 | 0% | |
| 94 | Document Impact Considerations of Changes to Forest after Deployment | 3 days | Wed 3/13/02 | Mon 3/18/02 | 0% | |
| 95 | Define schema change policy | 2 days | Wed 3/13/02 | Fri 3/15/02 | 0% | |
| 96 | Define configuration change policy | 1 day | Fri 3/15/02 | Mon 3/18/02 | 0% | |
| 97 | Document impact considerations of changes to forest after deployment complete | 0 days | Mon 3/18/02 | Mon 3/18/02 | 0% | |
| 98 | Document forest plan | 2 days | Mon 3/18/02 | Wed 3/20/02 | 100% | |
| 99 | Design Active Directory forest plan complete | 0 days | Wed 3/20/02 | Wed 3/20/02 | 0% | |
| 100 | Design Active Directory Domain Plan | 12 days | Wed 3/20/02 | Fri 4/5/02 | 88% | |
| 101 | Determine the Number of Domains in Each Forest | 5 days | Wed 3/20/02 | Wed 3/27/02 | 100% | |
| 102 | Evaluate single-domain model | 3 days | Wed 3/20/02 | Mon 3/25/02 | 100% | |
| 103 | Evaluate Multiple Domains Model | 2 days | Mon 3/25/02 | Wed 3/27/02 | 100% | |
| 104 | Evaluate preserving existing Windows NT 4.0 domains | 2 days | Mon 3/25/02 | Wed 3/27/02 | 100% | |
| 105 | Evaluate administrative partitioning considerations | 2 days | Mon 3/25/02 | Wed 3/27/02 | 100% | |
| 106 | Evaluate physical partitioning considerations | 2 days | Mon 3/25/02 | Wed 3/27/02 | 100% | |
| 107 | Multiple domains model complete | 0 days | Wed 3/27/02 | Wed 3/27/02 | 100% | |
| 108 | Assign a forest root domain | 4 hrs | Wed 3/27/02 | Wed 3/27/02 | 100% | |
| 109 | Assign a Domain Name System (DNS) name to each domain to create domain hierarchy | 4 hrs | Wed 3/27/02 | Thu 3/28/02 | 100% | |
| 110 | Plan a DNS server deployment | 2 days | Thu 3/28/02 | Mon 4/1/02 | 100% | |
| 111 | Optimize authentication with shortcut trusts | 2 days | Mon 4/1/02 | Wed 4/3/02 | 100% | |
| 112 | Document impact considerations of changes to domain after deployment | 2 days | Wed 4/3/02 | Fri 4/5/02 | 0% | |
| 113 | Design Active Directory domain plan complete | 0 days | Fri 4/5/02 | Fri 4/5/02 | 0% | |
| 114 | Design Active Directory Organizational Unit (OU) Plan | 6 days | Fri 4/5/02 | Mon 4/15/02 | 67% | |
| 115 | Define OUs to delegate administration | 2 days | Fri 4/5/02 | Tue 4/9/02 | 100% | |
| 116 | Define OUs to hide objects | 1 day | Tue 4/9/02 | Wed 4/10/02 | 100% | |
| 117 | Define OUs to apply Group Policy | 1 day | Wed 4/10/02 | Thu 4/11/02 | 100% | |
| 118 | Document impact considerations of changes to OU structures after deployment | 2 days | Thu 4/11/02 | Mon 4/15/02 | 0% | |
| 119 | Design Active Directory OU plan complete | 0 days | Mon 4/15/02 | Mon 4/15/02 | 0% | |
| 120 | Design a Site Topology Plan | 11.75 days | Mon 4/15/02 | Tue 4/30/02 | 99% | |
| 121 | Define Sites and Site Links Using the Physical Network Topology | 5 days | Mon 4/15/02 | Mon 4/22/02 | 100% | |
| 122 | Obtain physical network topology map | 4 hrs | Mon 4/15/02 | Mon 4/15/02 | 100% | |
| 123 | Create site for each LAN or set of LANs connected by high-speed backbone | 1 day | Mon 4/15/02 | Tue 4/16/02 | 100% | |
| 124 | Create a site for each location lacking direct connectivity (SMTP mail) | 1 day | Tue 4/16/02 | Wed 4/17/02 | 100% | |
| 125 | Record internet protocol (IP) subnets for each site | 4 hrs | Wed 4/17/02 | Thu 4/18/02 | 100% | |
| 126 | Site Links | 2 days | Thu 4/18/02 | Mon 4/22/02 | 100% | |
| 127 | Define site connections with site links | 1 day | Thu 4/18/02 | Fri 4/19/02 | 100% | |
| 128 | Define replication schedules | 1 day | Fri 4/19/02 | Mon 4/22/02 | 100% | |
| 129 | Define replication intervals | 0 days | Mon 4/22/02 | Mon 4/22/02 | 100% | |
| 130 | Define replication transports | 0 days | Mon 4/22/02 | Mon 4/22/02 | 100% | |
| 131 | Define link costs | 0 days | Mon 4/22/02 | Mon 4/22/02 | 100% | |
| 132 | Site links complete | 0 days | Mon 4/22/02 | Mon 4/22/02 | 100% | |
| 133 | Define Server Locations Within Sites | 6.25 days | Mon 4/22/02 | Tue 4/30/02 | 98% | |
| 134 | Define domain controller location per physical partition design | 1 day | Mon 4/22/02 | Tue 4/23/02 | 100% | |
| 135 | Define Additional Domain Controllers | 2 days | Tue 4/23/02 | Thu 4/25/02 | 100% | |
| 136 | Analyze failover requirements | 1 day | Tue 4/23/02 | Wed 4/24/02 | 100% | |
| 137 | Analyze domain controller client workload | 1 day | Wed 4/24/02 | Thu 4/25/02 | 100% | |
| 138 | Define additional domain controllers complete | 0 days | Thu 4/25/02 | Thu 4/25/02 | 100% | |
| 139 | Define location of global catalog servers | 2 hrs | Thu 4/25/02 | Thu 4/25/02 | 50% | |
| 140 | Define co existence with DNS servers | 3 days | Thu 4/25/02 | Tue 4/30/02 | 100% | |
| 141 | Document impact considerations of changes to site topology after deployment | 4 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% | |
| 142 | Design a site topology plan complete | 0 days | Tue 4/30/02 | Tue 4/30/02 | 100% | |
| 143 | Active Directory complete | 0 days | Fri 12/14/01 | Fri 12/14/01 | 0% | |
| 144 | Security Considerations | 57 days | Fri 12/21/01 | Tue 3/12/02 | 16% | |
| 145 | Identify the security risks that apply to your network | 1 wk | Fri 12/21/01 | Fri 12/28/01 | 100% | |
| 146 | Assess solutions for identifiable security risks | 3 days | Fri 12/28/01 | Wed 1/2/02 | 0% | |
| 147 | Ensure that all access to network resources requires authentication using domain accounts | 2 days | Wed 1/2/02 | Fri 1/4/02 | 0% | |
| 148 | Define the password length, change interval, and complexity requirements for domain user accounts, and develop a plan to communicate these requirements to the user community | 1 day | Fri 1/4/02 | Mon 1/7/02 | 0% | |
| 149 | Define policy for enabling remote access services | 2 days | Mon 1/7/02 | Wed 1/9/02 | 0% | |
| 150 | Develop procedures/communication regarding remote access procedures, including connection methods | 2 days | Wed 1/9/02 | Fri 1/11/02 | 0% | |
| 151 | Define user groups and establish conventions for group names and how group types are used | 3 days | Fri 1/11/02 | Wed 1/16/02 | 0% | |
| 152 | Define the top-level security groups you intend to use for broad security access to enterprise-wide resources | 1 day | Wed 1/16/02 | Thu 1/17/02 | 0% | |
| 153 | Define your access control policies with specific reference to how security groups are used | 2 days | Thu 1/17/02 | Mon 1/21/02 | 40% | |
| 154 | Define the procedures for creating new groups and who will have responsibility to manage group membership | 1 day | Mon 1/21/02 | Tue 1/22/02 | 50% | |
| 155 | Identify which existing domains belong in the forest and which domains will use external trust relationships | 1 day | Tue 1/22/02 | Wed 1/23/02 | 100% | |
| 156 | Describe your domains, domain trees, and forests, and explicitly state the trust relationships among them | 1 day | Wed 1/23/02 | Thu 1/24/02 | 100% | |
| 157 | Develop a deployment plan for using Internet Protocol Security (IPSec) for protection data for remote access or for accessing sensitive application data servers | 2 days | Thu 1/24/02 | Mon 1/28/02 | 0% | |
| 158 | If using Encrypting File System (EFS), describe your data recovery policy, including the role of recovery agent in your organization | 2 days | Mon 1/28/02 | Wed 1/30/02 | 0% | |
| 159 | If using EFS, describe the procedures you will use to implement data recovery process and verify the process works for your organization | 2 days | Wed 1/30/02 | Fri 2/1/02 | 0% | |
| 160 | If using IPSec, identify the scenarios for the way it will be used in your network and understand the performance implications | 2 days | Fri 2/1/02 | Tue 2/5/02 | 0% | |
| 161 | Define/communicate domain-wide account policies | 3 days | Tue 2/5/02 | Fri 2/8/02 | 0% | |
| 162 | Determine the local security policy requirements for different categories of systems on the network, such as desktops, file and print servers, e-mail servers, and define the Group Policy security settings appropriate to each category | 3 days | Fri 2/8/02 | Wed 2/13/02 | 0% | |
| 163 | Define application servers where specific security templates can be used to manage security settings, and consider managing them through Group Policy | 2 days | Wed 2/13/02 | Fri 2/15/02 | 0% | |
| 164 | Apply appropriate security templates for systems that upgrade from Windows NT 4.0 instead of a clean install | 1 day | Fri 2/15/02 | Mon 2/18/02 | 0% | |
| 165 | Use security templates as a means of describing the level of security you intend to implement for different classes of computers | 1 day | Mon 2/18/02 | Tue 2/19/02 | 0% | |
| 166 | Develop a test plan to verify your common business applications run correctly under properly configured secure systems | 1 wk | Tue 2/19/02 | Tue 2/26/02 | 0% | |
| 167 | Define what additional applications are needed that provide enhanced security features to meet your organization security objectives | 1 day | Tue 2/26/02 | Wed 2/27/02 | 0% | |
| 168 | State your policies for securing the administrator account and the administration consoles | 1 day | Wed 2/27/02 | Thu 2/28/02 | 0% | |
| 169 | Identify the situations where you plan to delegate administrator control for specific tasks | 1 day | Thu 2/28/02 | Fri 3/1/02 | 100% | |
| 170 | Identify your policies regarding auditing, including staffing | 2 days | Thu 1/10/02 | Fri 1/11/02 | 0% | |
| 171 | Document security strategy/standards | 1 wk | Mon 1/14/02 | Fri 1/18/02 | 0% | |
| 172 | Security considerations complete | 0 days | Mon 1/21/02 | Mon 1/21/02 | 0% | |
| 173 | Terminal Services | 10 days | Fri 12/14/01 | Fri 12/28/01 | 0% | |
| 174 | Select remote administration or server application mode | 2 days | Fri 12/14/01 | Tue 12/18/01 | 0% | |
| 175 | Develop a plan for implementing Terminal Services including networking, security, and remote access | 3 days | Tue 12/18/01 | Fri 12/21/01 | 0% | |
| 176 | Document detailed Terminal Services strategy/standards | 1 wk | Fri 12/21/01 | Fri 12/28/01 | 0% | |
| 177 | Terminal Services complete | 0 days | Fri 12/28/01 | Fri 12/28/01 | 0% | |
| 178 | Storage Management Strategies | 9.5 days | Fri 12/14/01 | Thu 12/27/01 | 0% | |
| 179 | Evaluate Windows 2000 Disk Management Strategies | 1 day | Fri 12/14/01 | Mon 12/17/01 | 0% | |
| 180 | Basic storage | 4 hrs | Fri 12/14/01 | Fri 12/14/01 | 0% | |
| 181 | Dynamic storage | 4 hrs | Mon 12/17/01 | Mon 12/17/01 | 0% | |
| 182 | Evaluate volume management | 1 day | Mon 12/17/01 | Tue 12/18/01 | 0% | |
| 183 | Evaluate mount points | 2 days | Tue 12/18/01 | Thu 12/20/01 | 0% | |
| 184 | Evaluate disk defragmentation strategies | 4 hrs | Thu 12/20/01 | Thu 12/20/01 | 0% | |
| 185 | Evaluate removable storage strategies | 1 day | Fri 12/21/01 | Fri 12/21/01 | 0% | |
| 186 | Evaluate remote storage strategies | 1 day | Mon 12/24/01 | Mon 12/24/01 | 0% | |
| 187 | Document storage management strategy/standards | 3 days | Tue 12/25/01 | Thu 12/27/01 | 0% | |
| 188 | Storage management strategies complete | 0 days | Thu 12/27/01 | Thu 12/27/01 | 0% | |
| 189 | Remediate Risk Assessment | 7 days | Fri 12/28/01 | Mon 1/7/02 | 0% | |
| 190 | Review risk assessment document | 1 day | Fri 12/28/01 | Fri 12/28/01 | 0% | |
| 191 | Identify solutions | 3 days | Mon 12/31/01 | Wed 1/2/02 | 0% | |
| 192 | Communicate to project sponsor, senior management, and project members | 1 day | Thu 1/3/02 | Thu 1/3/02 | 0% | |
| 193 | Evaluate risk as part of day-to-day project management | 2 days | Fri 1/4/02 | Mon 1/7/02 | 0% | |
| 194 | Remediate risk assessment complete | 0 days | Mon 1/7/02 | Mon 1/7/02 | 0% | |
| 195 | Develop Communications | 1.75 days | Tue 1/8/02 | Wed 1/9/02 | 0% | |
| 196 | Review communications strategy/standards | 2 hrs | Tue 1/8/02 | Tue 1/8/02 | 0% | |
| 197 | Develop communication materials | 2 hrs | Tue 1/8/02 | Tue 1/8/02 | 0% | |
| 198 | Review communications materials | 2 hrs | Tue 1/8/02 | Tue 1/8/02 | 0% | |
| 199 | Approve communications strategy and materials | 1 day | Tue 1/8/02 | Wed 1/9/02 | 0% | |
| 200 | Communication complete | 0 days | Wed 1/9/02 | Wed 1/9/02 | 0% | |
| 201 | Develop Education/training | 9 days | Tue 1/8/02 | Fri 1/18/02 | 0% | |
| 202 | Review training strategy/standards | 1 day | Tue 1/8/02 | Tue 1/8/02 | 0% | |
| 203 | Develop/acquire training materials | 1 wk | Wed 1/9/02 | Tue 1/15/02 | 0% | |
| 204 | Review education materials | 2 days | Wed 1/16/02 | Thu 1/17/02 | 0% | |
| 205 | Approve education strategy and materials | 1 day | Fri 1/18/02 | Fri 1/18/02 | 0% | |
| 206 | Develop training complete | 0 days | Fri 1/18/02 | Fri 1/18/02 | 0% | |
| 207 | Development complete | 0 days | Mon 1/21/02 | Mon 1/21/02 | 0% | |
| 208 | Proof of Concept (POC) | 9.5 days | Tue 3/12/02 | Tue 3/26/02 | 15% | |
| 209 | POC Preparation | 7.5 days | Tue 3/12/02 | Fri 3/22/02 | 17% | |
| 210 | Prepare a test plan and checklists based on development/design solutions | 3 days | Tue 3/12/02 | Fri 3/15/02 | 0% | |
| 211 | Document features and components to test | 2 days | Tue 3/12/02 | Thu 3/14/02 | 0% | |
| 212 | Secure resting personnel | 4 hrs | Mon 1/21/02 | Mon 1/21/02 | 0% | |
| 213 | Ensure the Testing Lab Environment Simulates the Proposed Production Environment | 7 days | Wed 3/13/02 | Fri 3/22/02 | 20% | |
| 214 | Server hardware and drivers | 2 days | Wed 3/13/02 | Fri 3/15/02 | 100% | |
| 215 | Services and configurations | 1 day | Wed 1/23/02 | Thu 1/24/02 | 0% | |
| 216 | User accounts | 1 day | Wed 1/23/02 | Thu 1/24/02 | 0% | |
| 217 | Domain structure (simulated domain hierarchy) | 2 days | Wed 3/13/02 | Fri 3/15/02 | 100% | |
| 218 | Server function/strategy | 2 days | Tue 1/22/02 | Thu 1/24/02 | 0% | |
| 219 | Mixed environment | 1 day | Wed 1/23/02 | Thu 1/24/02 | 0% | |
| 220 | Client computer configuration | 2 days | Tue 1/22/02 | Thu 1/24/02 | 0% | |
| 221 | Network topology and protocols | 2 days | Wed 3/13/02 | Fri 3/15/02 | 100% | |
| 222 | WAN connectivity | 2 days | Tue 1/22/02 | Thu 1/24/02 | 0% | |
| 223 | Remote connectivity | 1 day | Wed 1/23/02 | Thu 1/24/02 | 0% | |
| 224 | Peripherals | 3 days | Mon 1/21/02 | Thu 1/24/02 | 0% | |
| 225 | Amaint Integration | 7 days | Wed 3/13/02 | Fri 3/22/02 | 0% | |
| 226 | Interoperability with other operating systems (UNIX, mainframe, etc.) | 1 day | Wed 3/13/02 | Thu 3/14/02 | 60% | |
| 227 | Administrative tools | 2 days | Tue 1/22/02 | Thu 1/24/02 | 0% | |
| 228 | Fault tolerance techniques | 2 days | Tue 1/22/02 | Thu 1/24/02 | 0% | |
| 229 | Terminal Services | 2 days | Tue 1/22/02 | Thu 1/24/02 | 0% | |
| 230 | Ensure the testing lab environment simulates the proposed complete | 0 days | Thu 1/24/02 | Thu 1/24/02 | 0% | |
| 231 | POC preparation complete | 0 days | Thu 1/24/02 | Thu 1/24/02 | 0% | |
| 232 | Deploy Development Solution to POC (Production) Machines | 6 days | Mon 3/18/02 | Tue 3/26/02 | 0% | |
| 233 | Perform tests to test plan specification | 2 days | Thu 1/24/02 | Mon 1/28/02 | 0% | |
| 234 | Analyze results | 4 days | Mon 1/28/02 | Fri 2/1/02 | 0% | |
| 235 | POC complete | 0 days | Fri 2/1/02 | Fri 2/1/02 | 0% | |
| 236 | Pilot | 84.75 days | Fri 2/1/02 | Fri 5/31/02 | 0% | |
| 237 | Planning | 53.75 days | Fri 2/1/02 | Thu 4/18/02 | 0% | |
| 238 | Document resources and tasks | 2 days | Tue 3/26/02 | Thu 3/28/02 | 0% | |
| 239 | Ensure POC lab stable | 2 days | Tue 2/19/02 | Thu 2/21/02 | 0% | |
| 240 | Develop the Rollout Process | 17 days | Fri 2/1/02 | Tue 2/26/02 | 0% | |
| 241 | Identify tools and supplies the installer needs | 2 days | Fri 2/22/02 | Tue 2/26/02 | 0% | |
| 242 | Identify lists of scripts and their location | 3 days | Thu 2/21/02 | Tue 2/26/02 | 0% | |
| 243 | Document steps for deploying the new domain structure | 3 days | Fri 2/1/02 | Wed 2/6/02 | 0% | |
| 244 | Document steps for performing manual and automated computer upgrades | 2 days | Wed 2/6/02 | Fri 2/8/02 | 0% | |
| 245 | Document QA procedure | 2 days | Fri 2/8/02 | Tue 2/12/02 | 0% | |
| 246 | Document operational procedures installers and administrators are to perform (resetting permissions, changing passwords, etc.) | 3 days | Tue 2/12/02 | Fri 2/15/02 | 0% | |
| 247 | Document steps for backing out if pilot fails | 3 days | Fri 2/15/02 | Wed 2/20/02 | 0% | |
| 248 | Develop the rollout process complete | 0 days | Wed 2/20/02 | Wed 2/20/02 | 0% | |
| 249 | Identify known risks and contingency plans for them | 2 days | Wed 2/20/02 | Fri 2/22/02 | 0% | |
| 250 | Develop rollback plan | 2 days | Fri 2/22/02 | Tue 2/26/02 | 0% | |
| 251 | Pilot planning complete | 0 days | Tue 2/26/02 | Tue 2/26/02 | 0% | |
| 252 | Deployment | 12 days | Tue 2/26/02 | Thu 3/14/02 | 0% | |
| 253 | Communicate with pilot users | 4 hrs | Tue 3/5/02 | Tue 3/5/02 | 0% | |
| 254 | Conduct user training | 1 wk | Tue 2/26/02 | Tue 3/5/02 | 0% | |
| 255 | Ensure support organization is prepared | 4 days | Wed 2/27/02 | Tue 3/5/02 | 0% | |
| 256 | Prepare pilot site or sites | 2 days | Tue 3/5/02 | Thu 3/7/02 | 0% | |
| 257 | Deploy the rollout process | 1 wk | Thu 3/7/02 | Thu 3/14/02 | 0% | |
| 258 | Pilot deployment complete | 0 days | Thu 3/14/02 | Thu 3/14/02 | 0% | |
| 259 | Evaluate the Pilot | 8 days | Thu 3/14/02 | Tue 3/26/02 | 0% | |
| 260 | Conduct desktop test scenarios | 1 wk | Thu 3/14/02 | Thu 3/21/02 | 0% | |
| 261 | Conduct server test scenarios | 1 wk | Thu 3/14/02 | Thu 3/21/02 | 0% | |
| 262 | Conduct third-party application test scenarios | 1 wk | Thu 3/14/02 | Thu 3/21/02 | 0% | |
| 263 | Conduct custom application test scenarios | 1 wk | Thu 3/14/02 | Thu 3/21/02 | 0% | |
| 264 | Conduct coexistence test scenarios | 1 wk | Thu 3/14/02 | Thu 3/21/02 | 0% | |
| 265 | Identify scope changes | 3 days | Thu 3/21/02 | Tue 3/26/02 | 0% | |
| 266 | Identify cost factors | 2 days | Fri 3/22/02 | Tue 3/26/02 | 0% | |
| 267 | Identify interoperability issues | 3 days | Thu 3/21/02 | Tue 3/26/02 | 0% | |
| 268 | Identify unanticipated downtime | 2 days | Fri 3/22/02 | Tue 3/26/02 | 0% | |
| 269 | Pilot test complete | 0 days | Tue 3/26/02 | Tue 3/26/02 | 0% | |
| 270 | Post-Pilot Evaluation | 11 days | Tue 3/26/02 | Wed 4/10/02 | 0% | |
| 271 | Obtain user feedback | 1 wk | Tue 3/26/02 | Tue 4/2/02 | 0% | |
| 272 | Evaluate lessons learned | 2 days | Tue 4/2/02 | Thu 4/4/02 | 0% | |
| 273 | Modify items as necessary | 2 days | Thu 4/4/02 | Mon 4/8/02 | 0% | |
| 274 | Document recommendation for next steps | 2 days | Mon 4/8/02 | Wed 4/10/02 | 0% | |
| 275 | Post-pilot evaluation complete | 0 days | Wed 4/10/02 | Wed 4/10/02 | 0% | |
| 276 | Pilot complete | 0 days | Wed 4/10/02 | Wed 4/10/02 | 0% | |
| 277 | Deployment | 25.5 days | Wed 4/10/02 | Thu 5/16/02 | 0% | |
| 278 | Communication | 2.5 days | Wed 4/10/02 | Mon 4/15/02 | 0% | |
| 279 | Review communications strategy document | 2 days | Wed 4/10/02 | Fri 4/12/02 | 0% | |
| 280 | Start communications | 4 hrs | Fri 4/12/02 | Fri 4/12/02 | 0% | |
| 281 | Communications complete | 0 days | Mon 4/15/02 | Mon 4/15/02 | 0% | |
| 282 | Training | 11 days | Wed 4/17/02 | Thu 5/2/02 | 0% | |
| 283 | Review education/training strategy document | 1 day | Wed 4/17/02 | Wed 4/17/02 | 0% | |
| 284 | Conduct administrative training | 1 wk | Thu 4/18/02 | Wed 4/24/02 | 0% | |
| 285 | Conduct user training | 1 wk | Thu 4/25/02 | Wed 5/1/02 | 0% | |
| 286 | Education/training complete | 0 days | Thu 5/2/02 | Thu 5/2/02 | 0% | |
| 287 | Domain Deployment | 13 days | Mon 4/15/02 | Thu 5/2/02 | 0% | |
| 288 | Review domain migration strategy/standards document | 2 days | Mon 4/15/02 | Tue 4/16/02 | 0% | |
| 289 | Restructure existing Windows NT 4.0 domains | 1 wk | Wed 4/17/02 | Tue 4/23/02 | 0% | |
| 290 | Upgrade PDC to Windows 2000 | 4 hrs | Wed 4/24/02 | Wed 4/24/02 | 0% | |
| 291 | Upgrade BDCs to Windows 2000 | 1 day | Wed 4/24/02 | Thu 4/25/02 | 0% | |
| 292 | Upgrade resource domains | 1 day | Thu 4/25/02 | Fri 4/26/02 | 0% | |
| 293 | Member Server Migration | 3 days | Fri 4/26/02 | Wed 5/1/02 | 0% | |
| 294 | Review member server migration strategy/standards document | 1 day | Fri 4/26/02 | Mon 4/29/02 | 0% | |
| 295 | Backup files on servers to be upgraded | 4 hrs | Mon 4/29/02 | Mon 4/29/02 | 0% | |
| 296 | Upgrade member server | 4 hrs | Tue 4/30/02 | Tue 4/30/02 | 0% | |
| 297 | Test member server on network | 1 day | Tue 4/30/02 | Wed 5/1/02 | 0% | |
| 298 | Member server migration complete | 0 days | Wed 5/1/02 | Wed 5/1/02 | 0% | |
| 299 | Establish trusts | 4 hrs | Wed 5/1/02 | Wed 5/1/02 | 0% | |
| 300 | Domain migration complete | 0 days | Thu 5/2/02 | Thu 5/2/02 | 0% | |
| 301 | Security Infrastructure | 4 days | Fri 5/10/02 | Thu 5/16/02 | 0% | |
| 302 | Review security strategy/standards document | 4 hrs | Fri 5/10/02 | Fri 5/10/02 | 0% | |
| 303 | Create secure boundaries | 1 day | Fri 5/10/02 | Mon 5/13/02 | 0% | |
| 304 | Deploy strategies for everyone | 4 hrs | Mon 5/13/02 | Mon 5/13/02 | 0% | |
| 305 | Deploy strategies for company staff | 4 hrs | Tue 5/14/02 | Tue 5/14/02 | 0% | |
| 306 | Deploy strategies for users of company applications | 4 hrs | Tue 5/14/02 | Tue 5/14/02 | 0% | |
| 307 | Deploy strategies for partners | 1 day | Wed 5/15/02 | Wed 5/15/02 | 0% | |
| 308 | Security complete | 0 days | Thu 5/16/02 | Thu 5/16/02 | 0% | |
| 309 | Public Key Infrastructure | 10 days | Thu 5/2/02 | Thu 5/16/02 | 0% | |
| 310 | Review public key strategy/standards document | 1 day | Thu 5/2/02 | Thu 5/2/02 | 0% | |
| 311 | Providing training and support for production users | 1 wk | Fri 5/3/02 | Thu 5/9/02 | 0% | |
| 312 | Install CAs | 4 hrs | Fri 5/10/02 | Fri 5/10/02 | 0% | |
| 313 | Install/configure support systems or applications | 4 hrs | Fri 5/10/02 | Fri 5/10/02 | 0% | |
| 314 | Configure the certificates to be used | 4 hrs | Mon 5/13/02 | Mon 5/13/02 | 0% | |
| 315 | Configure certificate revocation lists publication | 4 hrs | Mon 5/13/02 | Mon 5/13/02 | 0% | |
| 316 | Configure public key Group Policy | 4 hrs | Tue 5/14/02 | Tue 5/14/02 | 0% | |
| 317 | Configure certificate renewal and enrollment | 4 hrs | Tue 5/14/02 | Tue 5/14/02 | 0% | |
| 318 | Issue certificates to users, computers, and services | 1 day | Wed 5/15/02 | Wed 5/15/02 | 0% | |
| 319 | Public key infrastructure complete | 0 days | Thu 5/16/02 | Thu 5/16/02 | 0% | |
| 320 | High-Availability Applications/Services (Clustering) | 6.5 days | Tue 5/7/02 | Thu 5/16/02 | 0% | |
| 321 | Review high availability applications/services (clustering) document | 1 day | Tue 5/7/02 | Wed 5/8/02 | 0% | |
| 322 | Optimize Windows 2000 cluster service | 1 day | Wed 5/8/02 | Thu 5/9/02 | 0% | |
| 323 | Choose tools to help you automate the deployment of Windows 2000 cluster service | 4 hrs | Thu 5/9/02 | Thu 5/9/02 | 0% | |
| 324 | Optimize your clusters | 1 day | Fri 5/10/02 | Fri 5/10/02 | 0% | |
| 325 | Plan for fault-tolerant disks | 1 day | Mon 5/13/02 | Mon 5/13/02 | 0% | |
| 326 | Test server capacity | 1 day | Tue 5/14/02 | Tue 5/14/02 | 0% | |
| 327 | Plan a backup and recovery strategy | 1 day | Wed 5/15/02 | Wed 5/15/02 | 0% | |
| 328 | High-availability applications/services (clustering) complete | 0 days | Thu 5/16/02 | Thu 5/16/02 | 0% | |
| 329 | Storage Management Strategies | 8.5 days | Fri 5/3/02 | Wed 5/15/02 | 0% | |
| 330 | Review storage management strategy/standards document | 1 day | Fri 5/3/02 | Mon 5/6/02 | 0% | |
| 331 | Review business requirements for storage | 4 hrs | Mon 5/6/02 | Mon 5/6/02 | 0% | |
| 332 | Design storage management solution | 2 days | Tue 5/7/02 | Wed 5/8/02 | 0% | |
| 333 | Design storage utilities (backup, restore, defragmentation) | 1 day | Thu 5/9/02 | Thu 5/9/02 | 0% | |
| 334 | Design disaster recovery plan | 2 days | Fri 5/10/02 | Mon 5/13/02 | 0% | |
| 335 | Document storage management strategy/standards | 1 day | Tue 5/14/02 | Tue 5/14/02 | 0% | |
| 336 | Storage management strategies complete | 0 days | Wed 5/15/02 | Wed 5/15/02 | 0% | |
| 337 | Switch to native mode | 1 day | Wed 5/15/02 | Wed 5/15/02 | 0% | |
| 338 | Deployment complete | 0 days | Thu 5/16/02 | Thu 5/16/02 | 0% | |
| 339 | Post-Implementation Review | 12 days | Thu 5/16/02 | Fri 5/31/02 | 0% | |
| 340 | Obtain user feedback | 1 wk | Thu 5/16/02 | Wed 5/22/02 | 0% | |
| 341 | Evaluate lessons learned | 4 days | Thu 5/23/02 | Tue 5/28/02 | 0% | |
| 342 | Modify items as necessary | 2 days | Wed 5/29/02 | Thu 5/30/02 | 0% | |
| 343 | Establish ongoing infrastructure planning team | 1 day | Fri 5/31/02 | Fri 5/31/02 | 0% | |
| 344 | Post-implementation review complete | 0 days | Fri 5/31/02 | Fri 5/31/02 | 0% |
| ID | Name | Group | Max Units | Peak Units |
|---|
| Task ID | Task Name | Resource Name | Work | Start | Finish | % Work Complete |
|---|