Schedule of AT-PSC Meetings for 2012
Generally the committee meets on the last Tuesday of each month. In order to adequately review and estimate new requests, new requests must be received 10 working days prior to the meeting.
Deadline for new Request Submission |
AT-PSC Meeting Date |
16 Jan 2012 |
31 Jan 2012 |
13 Feb 2012 |
28 Feb 2012 |
12 Mar 2012 |
27 Mar 2012 |
5 Apr 2012 |
24 Apr 2012 |
14 May 2012 |
29 May 2012 |
11 Jun 2012 |
26 Jun 2012 |
16 Jul 2012 |
31 Jul 2012 |
13 Aug 2012 |
28 Aug 2012 |
10 Sep 2012 |
25 Sep 2012 |
15 Oct 2012 |
30 Oct 2012 |
9 Nov 2012 |
27 Nov 2012 |
AT-PSC Process
Reporting to the AVPSI and CIO, the A&T Priority Setting Committee (AT-PSC) will assess and prioritize A&T supported application change requests to achieve optimal impact for stakeholders. This process will remain as the governance process for A&T Sustainment.
Each Work Request will follow the general steps outlined below:
- An end user defines the need for a modification to the system by filling out a Work Request Form.
- The request is forwarded to at-psc@sfu.ca along with the Business Area’s priority.
- The request is reviewed by the A&T Review Team.
- The AT-PSC reviews the request and makes a selection from the available options.
- Out of scope items or those requiring the approval of additional funds and resources, which the PSC feels should be considered further are escalated to the ADMIN IT. After a AT-PSC decision, the request is returned to the Review Team who action it appropriatly.