|
Chapter Contents |
Previous |
Next |
| The GANTT Procedure |
Fill patterns are specified using PATTERN statements, and the COMPRESS option is employed in order to draw the entire Gantt chart on one page. Predicted schedules as well as actual schedules are plotted on separate bars for each activity. The A_START= and A_FINISH= options in the CHART statement are used to specify the variables containing the actual start and finish times for each activity. The actual schedule is plotted with the fill pattern specified in the sixth PATTERN statement. This example also illustrates the drawing of holidays in graphics mode. PROC GANTT uses the fill pattern specified in the seventh PATTERN statement to represent the holidays defined by the HOLIDATA= data set. The holidays are identified to PROC GANTT by specifying the HOLIDAY= and HOLIFIN= options in the CHART statement. The HCONNECT option causes a connecting line to be drawn from the left boundary of the chart to the early start time for each activity. The CHCON= option specifies the color for drawing the connect lines. You can use the LHCON= option in the CHART statement to specify a line style other than the default style for the connect lines.
data complete;
format sdate date9. fdate date9.;
input activity $ 1-12 sdate date9. fdate date9.;
datalines;
Approve Plan 02dec91 06dec91
Drawings 07dec91 17dec91
Anal. Market 06dec91 10dec91
Write Specs 08dec91 13dec91
Prototype 18dec91 04jan92
Mkt. Strat. 11dec91 20dec91
Materials 03jan92 12jan92
Facility 02jan92 14jan92
Init. Prod. 14jan92 22jan92
Evaluate 23jan92 02feb92
Test Market 24jan92 09feb92
Changes 06feb92 12feb92
Production 13feb92 13feb92
Marketing 27jan92 27jan92
;
* merge the computed schedule with the actual schedule;
data widgela;
merge saveh complete;
* sort the data;
proc sort; by e_start;
title f=swiss 'Gantt Example 10';
title2 f=swiss
'Plotting Actual Start and Finish Times on the Chart';
* set vpos to 40 and hpos to 100;
goptions vpos=40 hpos=100;
* set up required pattern statements;
pattern1 c=green v=s; /* duration of a noncrit. activity */
pattern2 c=green v=e; /* slack time for a noncrit. act. */
pattern3 c=red v=s; /* duration of a critical activity */
pattern4 c=green v=s; /* slack time for a supercrit. act. */
pattern5 c=green v=e; /* duration of a supercrit. act. */
pattern6 c=cyan v=s; /* actual duration of an activity */
pattern7 c=black v=x1; /* break due to a holiday */
* plot the computed and actual schedules using proc gantt;
proc gantt data=widgela holidata=holidays;
chart / holiday=(holiday) holifin=(holifin)
a_start=sdate a_finish=fdate
dur=days cmile=blue
font=swiss ctext=blue
caxis=black
hconnect
compress
;
id task;
run;
Output 4.10.1: Plotting the Actual Schedule on the Gantt Chart
|
|
Chapter Contents |
Previous |
Next |
Top |
Copyright © 1999 by SAS Institute Inc., Cary, NC, USA. All rights reserved.