| Data Set GCPM1, Created with PROC CPM |
| Obs | Task | Succ1 | Days | _cal_ | E_START | E_FINISH | L_START | L_FINISH | T_FLOAT | F_FLOAT |
| 1 | Run Exp 1 | Analyze Exp 1 | 11 | Student | 01JUL96 | 16JUL96 | 01JUL96 | 16JUL96 | 0 | 0 |
| 2 | Analyze Exp 1 | Send Report 1 | 5 | Prof. | 17JUL96 | 23JUL96 | 17JUL96 | 23JUL96 | 0 | 0 |
| 3 | Send Report 1 | Run Exp 2 | 0 | Prof. | 24JUL96 | 24JUL96 | 24JUL96 | 24JUL96 | 0 | 0 |
| 4 | Run Exp 2 | Analyze Exp 2 | 11 | Student | 24JUL96 | 07AUG96 | 24JUL96 | 07AUG96 | 0 | 0 |
| 5 | Analyze Exp 2 | Send Report 2 | 4 | Prof. | 08AUG96 | 13AUG96 | 08AUG96 | 13AUG96 | 0 | 0 |
| 6 | Send Report 2 | Write Final Report | 0 | Prof. | 14AUG96 | 14AUG96 | 14AUG96 | 14AUG96 | 0 | 0 |
| 7 | Write Final Report | Send Final Report | 4 | Prof. | 14AUG96 | 19AUG96 | 14AUG96 | 19AUG96 | 0 | 0 |
| 8 | Send Final Report | 0 | Student | 20AUG96 | 20AUG96 | 20AUG96 | 20AUG96 | 0 | 0 | |
| 9 | Site Visit | 1 | Prof. | 18JUL96 | 18JUL96 | 18JUL96 | 18JUL96 | 0 | 0 |