![]() Chapter Contents |
![]() Previous |
![]() Next |
| The CALENDAR Procedure |
| Alias: | DURATION |
| Calendar: | Schedule |
| Interaction: | If you use both a DUR and a FIN statement, DUR is ignored. |
| Tip: | To produce a schedule calendar, you must use either a DUR or FIN statement. |
| Featured in: | All schedule calendars (see Examples ) |
| DUR variable; |
| Required Arguments |
| Range: | The duration may be a real or integral value. |
| Restriction: | This variable must be in the activities data set. |
| See also: | For more information on activity durations, see Activities Data Set and Calendar Data Set |
| Duration |
| If INTERVAL= . . . | Then the default length of the duration unit is . . . | |
|---|---|---|
| DAY (the default) | 24 hours | |
| WORKDAY | 8 hours | |