| The CALENDAR Procedure |
| Alias: | HOLIDURATION |
| Calendar: | Schedule |
| Default: | If you do not use a HOLIDUR or HOLIFIN statement, all holidays last one day. |
| Restriction: | Cannot use with a HOLIFIN statement. |
| Featured in: | Schedule Calendar with Holidays -- 5-Day Default through Schedule Calendar, Blank or with Holidays |
| HOLIDUR variable; |
| Required Arguments |
| Range: | The duration may be a real or integral value. |
| Restriction: | This variable must be in the holidays data set. |
| Featured in: | Multiple Schedule Calendars with Atypical Workshifts (Separated Output) and Multiple Summary Calendars with Atypical Workshifts (Separated Output) |
| Holiday Duration |