If the PROJECT statement is used, then a task's level in the project hierarchy is indicated in the Table View by using small square boxes to the left of the activity number in the Job Nbr column. Empty boxes indicate that the activity does not have any subtasks (it is a leaf activity), while filled boxes indicate that the activity is a supertask. Further, a Project Summary task is included to represent the root task (or Summary Task) of the project. This task is positioned at the top of the list of activities, and its display can be toggled on or off by selecting "Display Summary Task" from the "View" pull-down menu (see Figure 6.6).
In the Gantt View, supertasks are indicated by vertical cones at the end of their corresponding schedule bars.
Note that the durations of the supertasks are determined by the overall duration of their subtasks. Thus, you cannot change the duration of a supertask.
If there is no PROJECT statement, all menu selections that correspond to the multi-project structure are grayed out and are unavailable for selection. For example, the "Display Summary Task" selection in Figure 6.6 will be grayed out.
Chapter Contents |
Previous |
Next |
Top |
Copyright © 1999 by SAS Institute Inc., Cary, NC, USA. All rights reserved.